Cohen to face the aldermanic music on Newton North costs
NEWTON
Mayor David Cohen will meet with the Newton Board of Aldermen Monday night at 7:15 p.m. to address their questions about the $154 million Newton North High School building project.
President Lisle Baker made the request to the mayor last week, after many aldermen expressed frustration at the lack of communication and accountability from the executive office about additional costs and delays associated with numerous problems encountered at the building site and in the project management.
The issues that will be discussed include the discovery of asbestos and an underground ledge that must be removed through blasting -- both of which were not accounted for in the project's budget or timeline -- as well as the date the city will negotiate a guaranteed maximum price for the project with the contractor.
-- Rachana Rathi
This blogger might want to review your comment before posting it.