< Back to Front Page Text size +

No extra cash for Medfield senior center builder

Posted by Ralph Ranalli November 14, 2007 01:50 PM

MEDFIELD

The town will not pay the builder of the town's new senior center extra money for delays that were a result of weather last winter, Town Administrator Michael Sullivan said.

Braintree-based Northeast Interiors had asked the town to pay unspecified amounts of money to compensate for costs incurred during the delays. Sullivan said the town's contract with the developer clearly states that Northeast Interiors assumed the risk of weather delays.

The $3.1 million project was originally scheduled to be finished last July, but is now slated to be complete on Dec. 20.

-- Calvin Hennick

add your comment
Required
Required (will not be published)

This blogger might want to review your comment before posting it.

About globe west updates Welcome to Globe West Updates, the news blog of the Globe West regional section of The Boston Globe. Check in with us often to see updated items about Boston's western suburbs from our staff reporters and correspondents. Give us your reaction to our stories in the print editions or on the blog by using the form below. Get involved with Globe West!
archives