WTC site owners rewrite expectations

Process plagued by cost overruns, project delays

Deadlines for almost every project at the WTC site, pictured yesterday, have changed since being introduced in 2003. Deadlines for almost every project at the WTC site, pictured yesterday, have changed since being introduced in 2003. (Getty Images)
By Amy Westfeldt
Associated Press / October 3, 2008
  • Email|
  • Print|
  • Single Page|
  • |
Text size +

NEW YORK - The owners of the World Trade Center site scaled back designs for a multibillion-dollar transit hub yesterday and delayed other projects by several years, but said costs will still be more than $1 billion over budget.

In a 70-page report on ground zero's tortured rebuilding process, the Port Authority of New York and New Jersey said the elaborate rail hub will cost $3.2 billion, $700 million more than planned, and should open in 2014.

The planned memorial to the Sept. 11, 2001, attacks will be finished by the 10th anniversary, the report said, except that some of the 500 trees in a cobblestone plaza may not be planted and a visitor's center may not be open. Governor David Paterson and Mayor Michael Bloomberg had publicly urged the agency to guarantee completion by the anniversary.

An underground Sept. 11 museum should open in 2013, four years after that segment's initial completion date.

Completion of the signature project, a 1,776-foot Freedom Tower now under construction, is about $200 million over budget and will be delayed several months to 2013. Additional parts of the project are also over budget, bringing the final tally to more than $1 billion over estimates.

The agency did not set schedules for four other office towers planned for the site or for a performing arts center, and did not issue a final budget for the memorial.

"While we still face many challenges ahead, we believe we have created a level of certainty and control over this project that has been missing since its inception," the agency's executive director, Christopher Ward, said in a letter to Paterson.

Ward said the report reflects an understanding of the realities of building from scratch a complex of interconnected skyscrapers, transit links, and cultural space in a hole seven stories deep. He said he realized the new deadlines "will be met with a degree of skepticism."

Deadlines for almost every project at the site have changed since plans were first introduced in 2003.

Ward acknowledged the new schedule could also change.

"I cannot promise that we will meet every single milestone every step of the way," he wrote. "This is the most complex construction program in the region's history and setbacks are inevitable."

Most of the report seemed to involve transportation plans, including the rail hub designed by Santiago Calatrava and links to several subway lines, one of which sits in the midst of several construction projects.

  • Email
  • Email
  • Print
  • Print
  • Single page
  • Single page
  • Reprints
  • Reprints
  • Share
  • Share
  • Comment
  • Comment
 
  • Share on DiggShare on Digg
  • Tag with Del.icio.us Save this article
  • powered by Del.icio.us
Your Name Your e-mail address (for return address purposes) E-mail address of recipients (separate multiple addresses with commas) Name and both e-mail fields are required.
Message (optional)
Disclaimer: Boston.com does not share this information or keep it permanently, as it is for the sole purpose of sending this one time e-mail.