Fuel probably melted in 3 units, operator admits

Tokyo Electric acknowledged last week that fuel at Unit 1 (above) probably melted. Yesterday Unit 2 and 3 were added. Tokyo Electric acknowledged last week that fuel at Unit 1 (above) probably melted. Yesterday Unit 2 and 3 were added. (AFP/Getty Images)
By Hiroko Tabuchi
New York Times / May 25, 2011

E-mail this article

Invalid E-mail address
Invalid E-mail address

Sending your article

Your article has been sent.

Text size +

TOKYO — In a belated acknowledgment of the severity of Japan’s nuclear disaster, the Tokyo Electric Power Company said yesterday that three of the stricken Fukushima Daiichi plant’s reactors probably suffered fuel meltdowns in the early days of the crisis.

The plant’s operator also said that it was possible the pressure vessels in the three stricken reactors, which house the uranium fuel rods, had been breached as well. But most of the fuel remained inside the vessels, the company said — far from a more severe nuclear meltdown in which molten fuel penetrates the ground, a calamity known as the “China Syndrome.’’

Also yesterday, a team from the International Atomic Energy Agency, the nuclear oversight body of the UN, began an investigation into Japan’s handling of the accident, amid criticism that a slow response made matters worse.

“We’re here to gather info and to seek to learn lessons that we can apply across the world to improve nuclear safety,’’ Michael Weightman, the chief nuclear inspector of Britain and the team’s leader, said at a meeting with Japan’s trade minister, Banri Kaieda.

Yesterday’s disclosure by Tokyo Electric Power, the operator of the stricken Fukushima Daiichi Nuclear Power Station, could delay efforts to bring the plant’s reactors under control.

Earlier this month, the company released an updated plan to bring all reactors at the plant to a stable state known as a “cold shutdown’’ in six to nine months. But that goal was based on an understanding that workers could efficiently cool the fuel in the three reactors, a harder task if their inner pressure vessels are breached.

It is also likely to trigger more criticism over what many critics have called a lack of timely disclosure by Tokyo Electric, and by the Japanese government, of important details of the accident. Prime Minister Naoto Kan has apologized in Parliament for fanning public mistrust.

“We take this disclosure very seriously. But what’s important now is our response,’’ said Goshi Hosono, who heads the Japanese government’s nuclear crisis task force.

“Though we now know the situation is very severe, the fuel still remains inside the reactors,’’ Hosono said. “There is no change to our strategy of continuing to cool the reactors until we can bring them to a stable state.’’

Specialists had long suggested that meltdowns occurred at the three reactors after a tsunami knocked out power for their cooling systems, causing the nuclear fuel at the reactors’ cores to overheat.

Three other reactors at the Fukushima Daiichi plant, about 150 miles north of Tokyo, were not operating at the time of the March 11 earthquake and tsunami.

Tokyo Electric acknowledged last week for the first time that the fuel at one of the reactors, Unit 1, probably melted and fell to the bottom of the reactor’s inner pressure vessel.

Yesterday, Tokyo Electric said that meltdowns probably occurred at Units 2 and 3.

It took time to reach that conclusion because Tokyo Electric has been gradually retrieving data from the damaged plant and analyzing the findings, Junichi Matsumoto, a senior nuclear official at the company, said at a press conference.

Matsumoto said data showed that damage to Unit 2 began three days after the quake, when its backup cooling system failed, with most fuel rods eventually melting and collecting at the bottom of the pressure vessel. At Unit 3, fuel rods showed signs of damage by the afternoon of March 13.

But many of the details of how the accident unfolded remain murky. The 18-person team from the International Atomic Energy Agency includes specialists from the United States, China, Britain, and Russia.

They will interview officials at Tokyo Electric, as well as Japanese nuclear regulators, before drafting a preliminary report next month.

Boston.com top stories on Twitter

    waiting for twitterWaiting for Twitter to feed in the latest...