THIS STORY HAS BEEN FORMATTED FOR EASY PRINTING
< Back to front page Text size +

Dedham Square Construction schedule for week 26

Posted by Natalie Feulner  September 24, 2012 03:55 PM

E-mail this article

Invalid E-mail address
Invalid E-mail address

Sending your article

The Dedham Square Improvement Project construction is in its 26th week. Here's a look at work planned for this week downtown.

NEWS RELEASE:

1. The reconstruction of the sidewalk on the northerly side of High Street from Washington Street (Regina’s Bakery) to Court Street (Registry of Deeds) will begin. Work will consist of the installation of new granite curbing and the grading and forming for the pouring of the new concrete sidewalk. The brick banding will be installed in the sidewalk at a later date. The sidewalk will be temporarily closed for up to two weeks and the eight on-street parking spaces will be unavailable only when work in this area takes place. Temporary access ways through the construction area will be provided for all businesses and residential buildings while construction is ongoing.

2. The reconstruction of the sidewalk on the northerly side of High Street from Eastern Avenue (Ron’s Ice Cream) to Washington Street (Wardle’s Pharmacy) will continue this week. Work will consist of the pouring of the new concrete sidewalks. The sidewalk will be temporarily closed for up to one week and the seven on-street parking spaces will be unavailable only when work in this area takes place. Temporary access ways through the construction area will be provided for all businesses and residential buildings while construction is ongoing.

3. The installation of bricks for the brick banding located within the sidewalks will continue this week. On-street parking will be temporarily closed during work hours in the areas the contractor is conducting work and reopened again at the end of the work day.

4. The reconstruction of the Keystone Parking Lot retaining wall is scheduled to continue this week. Work will consist of the construction of the new concrete retaining wall, facing the concrete retaining wall with stone veneers cut from the existing retaining wall blocks and backfilling the retaining wall on the parking lot side to construct the remainder of the Keystone Parking Lot. Approximately 250 feet of sidewalk adjacent to the retaining wall from Eastern Avenue to the Route 1 bridge overpass will be closed for approximately four to eight weeks. The existing five parking spaces near the easterly half of the retaining wall currently under construction will be unavailable for approximately three to four weeks during the construction of the concrete retaining wall. The contractor anticipates on backfilling the westerly portion of the retaining wall that has been constructed to date this week. Once backfilled, the contractor should be able to move the jersey barriers back to the edge of the existing pavement which would provide room for some on-street parking for this area of High Street.

5. The contractor will be performing miscellaneous concrete work associated with the brick banding and tree frames for the sidewalks that have been poured to date. This work will take place on the street side half of the poured sidewalks where the proposed brick banding and tree frames are to be installed. The back half of the poured sidewalks should remain open for pedestrians. The on-street parking will be temporarily closed while work is taking place and reopened at the conclusion of the work day.

6. The installation of street trees and landscaping will continue this week. Street trees are anticipated to be installed on Washington Street and landscaping installed in the landscape areas around the police station. A couple of on-street parking spaces may be unavailable at various locations while work takes place.

7. Various utility companies will be working within the area of High Street near the retaining wall where the new utility poles have been installed over the next several months to switch their overhead utilities from the existing poles to the new poles. Once all the overhead utilities are switched over, the old poles will be removed.

Natalie Feulner can be reached at natalie.feulner@gmail.com.

E-mail this article

Invalid E-mail address
Invalid E-mail address

Sending your article