Making a center cut

Road-widening on Route 128 is still on track

The Route 128 widening project is making progress, as seen from a bridge over the highway near the Houghton’s Pond exit in Milton. The Route 128 widening project is making progress, as seen from a bridge over the highway near the Houghton’s Pond exit in Milton. (Jonathan Wiggs/Globe Staff)
By Robert Preer
Globe Correspondent / August 5, 2010

E-mail this article

Invalid E-mail address
Invalid E-mail address

Sending your article

Your article has been sent.

Text size +

In the median of Route 128, encampments of construction workers, State Police cruisers, and heavy equipment have become familiar sights for motorists south of Boston. Lane shifts, daytime slowdowns, and late-night backups also are routine. (Full article: 864 words)

This article is available in our archives:

Globe Subscribers

FREE for subscribers

Subscribers to the Boston Globe get unlimited access to our archives.

Not a subscriber?

Non-Subscribers

Purchase an electronic copy of the full article. Learn More

  • $9.95 1 month archives pass
  • $24.95 3 months archives pass
  • $74.95 1 year archives pass
    waiting for twitterWaiting for Twitter to feed in the latest...